Remediation by steam-air-injection - City of Villingen-Schwenningen, Germany
- Abstract
-
Remediaton by steam air injection into fractured rock at a site in Biswurm, Germany
This is a follow-up project to: Pilotuntersuchung Dampf-Luft-Injektion im Kluftgestein - Standort Biswurm - Project manager
-
Haslauer, Claus
- Deputy
-
- Research assistants
-
Trötschler, Oliver
- Department
-
VEGAS
- Duration
-
From: 2011-01-12
To: 2020-09-30
- Finances
-
Stadt Villingen-Schwenningen, Regierungspräsidium Freiburg (Altlastenfond Land Baden-Württemberg)
- Cooperation partners
-
GEOsens Ingenieurpartnerschaft, Ebringen